1300 088 065

Construction and renovation

How do construction loan progress payments work?

Your builder requests payment after completing an agreed stage. You check the work and invoice, then ask the lender to release that part of the construction loan. The lender may need more documents or an inspection before it pays.

New homes under construction with exposed timber wall and roof frames

A progress payment releases part of your construction loan to pay for an agreed stage of building work. You may also hear it called a draw. The money is released in stages as the build progresses, subject to the lender's checks.

If an invoice is already due or the amount looks wrong, go straight to what to do about an invoice problem. Otherwise, start with the stages and what needs to be ready for the first payment.

Which building stages do progress payments cover?

You will commonly see these names in a building schedule. The work included in each stage, the number of payments and the amounts depend on your signed contract and the schedule your lender approves.

  • Base: preparation of the site and the slab or foundations.
  • Frame: the structural frame of the home.
  • Lock-up or enclosed: the roof, external walls, windows and doors bring the home to an enclosed stage.
  • Fixing: internal work such as wall linings, doors, cabinets and fittings.
  • Completion: the agreed building work reaches the final stage, with final checks and documents still needed before the lender pays.

There is no percentage schedule that applies to every build. Use your contract and the lender's approved schedule, and check exactly what work the builder must complete before claiming each amount. The construction finance guide has a worked example.

What needs to be ready before the first payment?

Confirm when your own contribution must be paid and how the builder's deposit will be covered. A deposit due under the building contract and the cash the lender requires you to contribute are separate checks. Do not assume the first loan payment will reimburse a deposit you have already paid.

CommBank, for example, requires your contribution before its progress payments begin. Ask the broker or lender managing your loan what must happen before it is ready to release money, which documents are still missing and how to show that your contribution has been used.

  • Confirm the builder and lender are working from the same contract, plans and payment schedule.
  • Ask which approvals, insurance documents and other conditions must be satisfied before money can be released.
  • Confirm the lender's submission channel, who gives payment authority and whether the first stage needs an inspection.

For the earlier steps, including land settlement, see how construction finance works.

How do you request each progress payment?

  1. Builder issues the claim
  2. You check the stage and amount
  3. The claim and authority go to the lender
  4. Evidence or an inspection is completed
  5. The lender releases the approved payment

What should you check before each builder invoice?

Before sending a request, I check four things: the amount claimed, the amount approved for that stage, any lender-approved changes and whether the documents or inspection are ready.

In Queensland, QBCC says payments should follow the contract and work completed. Paying early or above the required amount can reduce home warranty protection. Get advice if the stage is disputed.

Send the invoice and your payment authority through the channel your lender specifies. Bankwest's payment instructions are one example: customers must authorise each payment, and the bank may arrange an inspection.

ANZ asks for its signed payment instruction with the builder's invoice. If you paid the builder yourself and want that amount back from the loan, ANZ has a separate process that needs your receipt. Confirm the arrangement before spending your savings.

How long does payment take, and what can delay it?

Ask the managing lender when it expects to release the payment and whether that timeframe begins only after it has a complete request. Send the documents promptly and check whether an inspection needs to be booked. There is no reliable timeframe that applies to every lender and every claim.

Tell your broker or lender the invoice due date when you send it. If the expected release is later, contact them and the builder early to establish what needs to happen. The contract due date does not remove the lender's payment conditions.

Most construction loans follow the same broad sequence, but the detail is not identical. Some lenders publish set stage limits. Others work from the payment schedule in the accepted building contract. Inspections can happen at selected stages, every stage or only when something needs checking.

What I check with each lender
What can varyWhat I check
Stage amountsDoes the builder's invoice match the payment schedule the lender approved?
Your cash contributionDoes your cash need to be used before the lender starts paying builder invoices?
InspectionsWhich stages need a valuer or inspector, and has site access been arranged?
VariationsHas the lender accepted the changed cost, or has only the builder accepted it?
Final paymentWhich completion documents and final inspection are needed before the last amount is released?

What I check with each lender

What can vary

Stage amounts

What I check
Does the builder's invoice match the payment schedule the lender approved?
What can vary

Your cash contribution

What I check
Does your cash need to be used before the lender starts paying builder invoices?
What can vary

Inspections

What I check
Which stages need a valuer or inspector, and has site access been arranged?
What can vary

Variations

What I check
Has the lender accepted the changed cost, or has only the builder accepted it?
What can vary

Final payment

What I check
Which completion documents and final inspection are needed before the last amount is released?

Variations are covered in more detail in what a fixed-price contract leaves out.

For example, NAB's guide identifies inspections before construction and at the first and final claims for registered-builder projects. Use your own lender’s issued schedule.

Until the lender confirms the draw, don't treat the undrawn part of the loan as money you can spend. And a change the builder has agreed to doesn't increase your loan unless the lender accepts it too.

What if the invoice is wrong or the payment is delayed?

Here's an example. The builder claims $101,500. The lender approved $92,000 for this stage and has separately accepted a $6,000 variation. That's $98,000, so $3,500 of the claim needs explaining before it's paid. (This assumes the variation isn't already inside the $92,000.) If the payment is due in 6 days, sort out the difference now and check whether the lender needs an inspection first.

Invoice check results and what to do next
ResultWhat it usually tells youNext step
Ready to submitThe claim fits the approved stage and variations, with the known evidence ready.Send the invoice and borrower authority through the lender's required process.
Amount mismatchThe claim is above or below the approved amount.Ask the builder to separate the stage, approved variations and any other amount.
Evidence missingThe amount matches, but the bank is still waiting on a document or inspection before it can release the money.Confirm exactly what is required and who must provide it.
Potential funding gapThe amount may not be covered by the approved stage and lender-approved changes.Do not promise payment. Work out the full amount needed to finish with the current broker or lender.

Invoice check results and what to do next

Result

Ready to submit

What it usually tells you
The claim fits the approved stage and variations, with the known evidence ready.
Next step
Send the invoice and borrower authority through the lender's required process.
Result

Amount mismatch

What it usually tells you
The claim is above or below the approved amount.
Next step
Ask the builder to separate the stage, approved variations and any other amount.
Result

Evidence missing

What it usually tells you
The amount matches, but the bank is still waiting on a document or inspection before it can release the money.
Next step
Confirm exactly what is required and who must provide it.
Result

Potential funding gap

What it usually tells you
The amount may not be covered by the approved stage and lender-approved changes.
Next step
Do not promise payment. Work out the full amount needed to finish with the current broker or lender.

Find out what is holding up the payment

Ask the lender exactly what is missing or does not match. Start with the invoice, approved payment schedule and your payment authority. Then provide the inspection result, lender-approved variation or proof of your contribution that it needs. You do not need to resend every document if one item is holding things up.

If the difference affects the money left for later stages, work out the full cost to finish with the broker or lender managing the loan before agreeing to another payment plan.

What will you repay during construction?

Construction interest is generally calculated on the amount already drawn, subject to the loan terms. That is why the payment often starts lower and rises as the house takes shape.

The amount charged interest grows with the build

  • Early stage

    $100k
  • Later stage

    $400k
  • Completed

    $600k

These figures are examples of the total loan balance already drawn at different points in the build. They are not individual builder invoices or monthly repayments. The amount of interest depends on the balance, rate and time outstanding.

Simple example only. Your rate, draw amounts and repayment method come from your loan documents.

The lender may still assess whether you can afford the full finished loan, even while interest is being charged on a smaller drawn balance during the build.

Ask whether your loan has progress-payment or inspection fees and when they are charged. Include the repayments, fees and any rent or existing mortgage in your budget while construction is underway.

What happens at practical completion?

The last claim usually needs more than the final invoice. Depending on the lender and project, there may be a final inspection, occupancy or completion documents, insurance evidence and confirmation that your contribution has been used.

For example, Westpac requires a satisfactory final inspection and building insurance cover note before its final payment. Ask for your lender’s completion checklist early.

Check the home carefully before authorising payment. The lender's inspection is for its lending decision. It is not a substitute for your own building inspection or legal advice, and it does not settle a dispute about defective or incomplete work.

Frequently asked questions

Check your next claim before the due date

If Hunter Galloway is managing your construction loan, send us the invoice, approved stage schedule, variation documents and due date. We can check what the lender needs before the request is submitted. If another lender or broker is managing an urgent claim, contact them first so the existing payment process can be followed.

or call 1300 088 065

Your full financial situation would need to be reviewed before any offer or product is accepted.

Related guides

Experience and sources

How this guide was checked

Public lender and Queensland building guidance checked on 22 September 2026. Each payment remains subject to the requirements for your loan and building contract.

Written byJoshua VecchioDirector & Mortgage Broker

Joshua Vecchio is a mortgage broker and director at Hunter Galloway. Hunter Galloway Finance Pty Ltd is Credit Representative 476903, authorised under Australian Credit Licence 389328. He holds a Certificate IV in Financial Services (Finance/Mortgage Broking) and a Diploma of Financial Services (Finance/Mortgage Broking Management).

Hunter Galloway Finance Pty Ltd, Credit Representative 476903, is authorised under Australian Credit Licence 389328. General information only, not a credit assessment, building inspection, valuation, legal advice or promise of payment or approval.