1300 088 065

Construction and renovation

How do construction loan progress payments work?

Your builder requests payment after completing an agreed stage. You check the work and invoice, then ask the lender to release that part of the construction loan. The lender may need more documents or an inspection before it pays.

Having an approved construction loan does not mean every builder invoice can be paid immediately. The amount, stage and evidence still need to match the lender's requirements.

The sequence is:

  1. Step 1
    The builder completes a stage and issues the claim
  2. Step 2
    You check the work, amount and due date
  3. Step 3
    You send the invoice and required authority to the lender
  4. Step 4
    The lender completes its checks, including an inspection if needed
  5. Step 5
    The accepted payment is released and your drawn loan balance increases

1. Match the invoice to the approved stage

Read the builder's invoice beside the payment schedule the lender accepted. Check the stage name, amount due and any variations included. A variation is a change to the original building contract; it may change the price, work or timing.

The schedule might refer to base, frame, lock-up, fixing and completion. Use the descriptions in your own contract rather than assuming a generic stage name proves the work is finished.

In Queensland, QBCC says progress payments should relate to the work completed and follow the contract. Paying more or earlier than the contract requires can reduce home warranty protection. If you disagree with a claim, get advice about the work and payment obligation before authorising it or withholding payment. QBCC progress-payment guidance

A matching total does not answer every question

An invoice may include the original stage, an agreed upgrade and a separate extra cost. Ask the builder to itemise them so the lender can see what it is being asked to pay.

You also need to know whether a variation was accepted for finance. Signing a change with the builder does not, by itself, increase your loan or the amount approved for that stage.

Example: finding an unexplained $3,500

Suppose the builder's invoice is $101,500, the approved stage amount is $92,000, and the lender has accepted an additional $6,000 for a variation.

Example: finding an unexplained $3,500
CheckAmount
Builder's invoice$101,500
Approved stage amount$92,000
Additional variation accepted for this payment$6,000
Total recognised for this payment$98,000
Amount still to explain$3,500

Example: finding an unexplained $3,500

Check

Builder's invoice

Amount
$101,500
Check

Approved stage amount

Amount
$92,000
Check

Additional variation accepted for this payment

Amount
$6,000
Check

Total recognised for this payment

Amount
$98,000
Check

Amount still to explain

Amount
$3,500

This example assumes the $6,000 has not already been included in the $92,000 stage amount. Otherwise, adding it again would overstate the money available.

With 6 days until the invoice is due, the next step is to identify the $3,500 and confirm any inspection requirement. It might be an invoice error or a cost outside the accepted payment. The calculation does not tell you which, and it does not promise the lender can pay within 6 days.

2. Confirm your contribution and the documents needed

Some of the early building payments may need to come from your savings. Ask the lender when your agreed contribution must be used and what evidence it needs before the first loan payment.

CommBank's construction timeline says a borrower's own contribution must be used before it starts progress payments. Other loan arrangements need their own check. Keep invoices and receipts, and do not assume every amount you pay early can be reimbursed. CommBank construction timeline

For the next claim, start with:

  • the builder's itemised invoice;
  • the approved stage schedule;
  • your signed payment instruction or other borrower authority;
  • any variation documents and the lender's response; and
  • evidence of your contribution, where required.

Use the lender's current process. For example, ANZ's handbook calls for a signed Progress Payment Instruction form and the builder's invoice. The first payment can also depend on construction commencement requirements being complete. ANZ construction handbook

If the bank is waiting for one missing item, establish exactly what it is and who needs to provide it. Sending the same incomplete pack again will not resolve that hold.

Can the bank reimburse a payment you already made?

Sometimes, under the lender's process. ANZ describes reimbursement using a receipt where the borrower has paid the builder directly, for an amount in the payment schedule. Confirm the arrangement before using your savings; do not assume another lender will follow it or that a payment outside the approved schedule will qualify. ANZ payment guidance

3. Allow for inspections before the invoice is due

There is no single turnaround time for all construction payments. A complete request, a clear invoice and access to the site help, but the lender still needs time for its checks.

Ask the person managing your loan:

  • Is an inspection required for this stage?
  • Has it been ordered, and can the valuer access the site?
  • Does anything else need to be supplied before payment?
  • What is the current processing time once everything is ready?

NAB's published guide identifies inspections before construction and at the first and final progress claims for registered-builder projects. Other lenders may use different inspection points. Do not copy one lender's schedule onto another loan. NAB building and renovation guide

A lender inspection supports the lending decision. It does not replace your own inspection of the quality and completeness of the work. If you need an independent building inspection, arrange that separately.

What if the payment is already urgent?

Contact the broker or lender managing the existing construction loan. Give them the due date and ask which exact condition remains outstanding. They hold the approval, previous draws and payment instructions needed to deal with the immediate request.

If payment may miss the contractual deadline, speak with the builder and get advice on your obligations. Do not promise that a new broker or another lender can immediately release money under the existing loan.

4. Resolve a mismatch before agreeing to extra work

Work out whether the problem is the paperwork or the funding. A corrected invoice can resolve one; it cannot create extra approved borrowing.

4. Resolve a mismatch before agreeing to extra work
What you findWhat to do next
The invoice has the wrong stage or amountAsk the builder to correct or explain it
The amount matches, but a document is missingSupply the specific item the lender requests
The stage needs an inspectionArrange access and confirm the inspection and processing sequence
The invoice includes a variationCheck whether the lender accepted the changed cost and payment
The approved money will not cover the workRecalculate the full cost to finish with the existing lender or broker

4. Resolve a mismatch before agreeing to extra work

What you find

The invoice has the wrong stage or amount

What to do next
Ask the builder to correct or explain it
What you find

The amount matches, but a document is missing

What to do next
Supply the specific item the lender requests
What you find

The stage needs an inspection

What to do next
Arrange access and confirm the inspection and processing sequence
What you find

The invoice includes a variation

What to do next
Check whether the lender accepted the changed cost and payment
What you find

The approved money will not cover the work

What to do next
Recalculate the full cost to finish with the existing lender or broker

For a genuine shortfall, include the remaining contract stages, changes, rectification and work outside the contract. Compare them with the undrawn loan and cash still available. You can draw on the unused approved loan only when the lender's conditions are met.

Do not sign further changes on the assumption that the bank will increase the loan. If more borrowing is needed, the lender may have to reconsider the repayment and finished property value. If it cannot provide more, another funding plan is needed before the extra cost is committed.

If the disagreement concerns incomplete or defective work, the builder's contractual entitlement and the bank's willingness to lend are separate questions. Ask a building adviser or solicitor about the work and contract. The broker can explain the funding position.

For the full budget and approval sequence, see how construction finance works.

5. Update your budget as each payment is made

Your drawn loan balance normally increases as construction payments are released. If the rate stays the same, a larger balance means more interest.

For a simple example at 6% a year:

5. Update your budget as each payment is made
Amount already drawnApproximate monthly interest
$100k$500
$400k$2,000
$600k$3,000

5. Update your budget as each payment is made

Amount already drawn

$100k

Approximate monthly interest
$500
Amount already drawn

$400k

Approximate monthly interest
$2,000
Amount already drawn

$600k

Approximate monthly interest
$3,000

These figures use the balance multiplied by 6%, divided by 12. They illustrate the calculation only; your current rate and repayment schedule may differ. Actual interest depends on daily balances, payment dates, the rate and loan terms. They also exclude fees and any separate mortgage or land loan.

If you are renting during the build, include rent alongside the rising interest. Allow for a delay in moving in as well. The amount due near the start of the build is not the amount your budget must carry near completion.

Interest-only payments cover interest without reducing the debt. Check the repayment that will apply when that period ends, using the full expected loan amount rather than only the first few draws.

6. Prepare for the final payment before handover

The final claim may need more than the last invoice. Ask the lender for its completion checklist early enough to arrange documents and an inspection.

Depending on the lender, state and project, the requirements may include an occupancy or final inspection certificate, building insurance and confirmation that the work matches the approved plans. Westpac requires a satisfactory final inspection and a new building insurance cover note before its final progress payment. Westpac construction guidance

Check any incomplete items or defects with your building adviser before authorising the final claim. A bank inspection or payment is not legal advice that all obligations under the building contract have been satisfied.

Also ask when your repayment changes and what happens to any money left in the loan. CommBank switches to the repayment type selected at application after its final progress payment. Other arrangements can depend on the agreed interest-only term. Use the dates and repayment terms in your own documents. CommBank construction loans

Progress-payment FAQs

Experience and sources

How this guide was checked

Public lender and Queensland building guidance checked on 22 September 2026. Each payment remains subject to the requirements for your loan and building contract.

Written byJoshua VecchioDirector & Mortgage Broker

Joshua Vecchio is a mortgage broker and director at Hunter Galloway. Hunter Galloway Finance Pty Ltd is Credit Representative 476903, authorised under Australian Credit Licence 389328.

Hunter Galloway Finance Pty Ltd, Credit Representative 476903, is authorised under Australian Credit Licence 389328. General information only, not a credit assessment, building inspection, valuation, legal advice or promise of payment or approval.

Related guides

Check your next claim before the due date

If Hunter Galloway is managing your construction loan, send us the invoice, approved stage schedule, variation documents and due date. We can check what the lender needs before the request is submitted. If another lender or broker is managing an urgent claim, contact them first so the existing payment process can be followed.

or call 1300 088 065

Your full financial situation would need to be reviewed before any offer or product is accepted.