1300 088 065

Construction and renovation

How do you finance a knockdown rebuild?

Get the construction finance approved and the lender's demolition conditions in writing before removing the existing home. Once the house is gone, the property value and available lenders can change.

Earthmoving equipment preparing a residential building site in Clyde North, Victoria

Client story

Aaron and Rebecca were told to demolish first and apply afterwards

Their existing home was worth about $685k with a $500k mortgage. Demolition was $25k and the new building contract was about $311k.

The first lender wanted the old house removed before it would give formal construction approval. That would have left them with a vacant block, a $500k mortgage and no confirmed build loan if the application failed.

I found another lender that could approve the project using a land-only value of $620k and a finished value of $1.12m. The full $810k loan was approved before demolition.

They demolished after approval, then the new home was funded through the 5 agreed progress stages.

What is the safest order for a knockdown rebuild?

  1. Confirm the current mortgage and title
    Check the debt, current value and whether any other property or loan is linked to the home.
  2. Price the demolition and complete build
    Add costs outside the building contract and enough cash for surprises.
  3. Test the finished repayment
    Include rent or temporary housing while construction interest grows.
  4. Get the land and finished valuations
    The lender may look at the property before demolition, as vacant land and when the new home is complete.
  5. Clear the loan conditions
    Confirm the acceptable builder, contract, plans, cash contribution, insurance and demolition requirements.
  6. Demolish only after approval
    Follow the lender's written sequence and get legal, planning and building advice before acting.
  7. Pay the builder in stages
    The lender releases the building money as the agreed work is completed and checked.

Loan approval, permission to demolish and approval to release the first payment are separate checks. Get the sequence in writing before work starts.

What happens to your existing mortgage?

The mortgage stays in place when the house comes down. Include it in the new loan plan, along with any fixed-rate commitments or other property securing the debt.

Compare your current lender with alternatives that accept the demolition and build. For example, ANZ’s handbook sets out how an existing land loan can fit into its construction finance. Check the arrangement for your own loan.

What needs to go into your build budget?

I put the current mortgage and every cost around the contract into one budget:

  • current mortgage or land purchase
  • demolition, disconnection and site clearing
  • the fixed-price building contract
  • design, engineering and council approvals
  • soil, retaining, drainage and service work outside the contract
  • driveway, fencing, landscaping, window coverings and appliances
  • rent, storage and moving twice
  • a separate cash buffer for delays and variations

Do not use the entire cash deposit on the property purchase and assume the later build will look after itself. The lender may require your agreed contribution to be used before it releases construction money.

Even if the loan covers demolition, you may need to pay the contractor before the bank releases that money. Check payment dates for demolition, disconnections, design fees and deposits, then confirm which costs need to come from your savings.

Our progress-payment guide explains what needs to be ready before the lender pays each building stage.

Which property value does the bank use?

  • Before demolition

    The home and land as they stand today.

  • After demolition

    The vacant land value, which can be lower once the house is gone.

  • When complete

    The lender's estimate of the new home and land after the approved build.

The finished value does not have to equal the current value plus every dollar spent. If the bank's accepted value is lower than the total project cost, you may need more cash even if you can afford the repayments.

Lenders can use different valuation instructions and demolition requirements. I compare those requirements alongside the rate to check which arrangement fits the whole project.

Your land’s value may help support the loan, but the lender still checks the existing debt, total borrowing and affordability. You may need cash for early costs and your agreed contribution. Our home equity guide explains what you may be able to borrow.

Map rent and repayments during the build

You may be paying rent while the bank releases the construction loan in stages. The interest amount can start lower and rise after each payment to the builder.

I would test 3 periods separately:

  • the time between moving out and the first progress payment
  • rent plus increasing construction interest during the build
  • the full home loan repayment after handover

Also leave room for a delay. Aaron and Rebecca expected to rent for about 8 months at $650 a week. One extra month would have meant another $2,800 or so before storage, moving or construction interest.

If an existing loan stays separate, include those repayments too. Interest-only payments do not reduce the loan balance; use the repayment calculator to check repayments after completion.

Check the lease, the builder’s latest schedule and the lender’s construction deadlines if the build is delayed. Contact the lender early if repayments may become difficult; repayment assistance does not itself fund the remaining build.

What must be confirmed before demolition?

  • formal loan approval and every outstanding condition
  • written confirmation of the demolition sequence
  • the demolition quote, permits and service disconnections
  • the signed building contract, plans and specifications
  • the accepted land-only and finished values
  • the cash contribution and when it must be used
  • builder, insurance and progress payment requirements
  • rent, storage and a delay buffer

In Brisbane, heritage and character controls can affect what you may demolish. Check planning permissions, service disconnections, waste and asbestos requirements, and insurance for demolition and construction. Our Brisbane building guide covers the local checks.

Confirm the finance is ready before agreeing to the builder's start date. Tell your broker and lender if the price, builder or design changes after approval.

Questions about knockdown rebuild finance

Client examples are based on real situations. Names and identifying details have been changed.

Experience and sources

How this guide was checked

Reviewed 23 September 2026 by Nathan Vecchio.

Written byJoshua VecchioDirector & Mortgage Broker

Joshua Vecchio is a mortgage broker and director at Hunter Galloway. Hunter Galloway Finance Pty Ltd is Credit Representative 476903, authorised under Australian Credit Licence 389328. He holds a Certificate IV in Financial Services (Finance/Mortgage Broking) and a Diploma of Financial Services (Finance/Mortgage Broking Management).

General information only. Lender requirements and the accepted valuation depend on the project and current assessment. Obtain independent legal, planning, building and insurance advice before signing contracts or authorising demolition.

Related guides

Map the loan before demolition

Send us the current mortgage balance, demolition quote, building tender or contract, available cash and expected rent during the build. We'll work through the total funding and the order of approvals and payments before the property changes.

or call 1300 088 065

Your full financial situation would need to be reviewed before any offer or product is accepted.